316 stainless pipe welding.

Specialist workshop and on-site welding completed as part of a heat exchanger refurbishment.

DN350 Schedule 10 316 stainless pipe welding for Royal Perth Hospital
Royal Perth Hospital / specialist stainless pipe welding

Specialist Stainless Pipe Welding.

Niche Welding was engaged to complete the specialist 316 stainless steel welding scope as part of a heat exchanger refurbishment at Royal Perth Hospital.

The works included DN350 Schedule 10 stainless steel pipework, socket and flange connections, using correct purge welding techniques throughout. The scope included both workshop welding and on-site in-position welding during installation.

Project
Heat exchanger refurbishment
Client site
Royal Perth Hospital
Material
316 stainless steel
Pipework
DN350 Schedule 10
Process
TIG / purge welding
Scope
Workshop & on-site specialist welding